VC Strategic Goal 5: Implement the Ventura College East Campus educational plan.

VC Objective 6: Explore opportunities for reconfiguring existing or acquiring new space to accommodate growth; reconfigure the East Campus curriculum.

VCCCD Board Goal: Access and Student Success 

#

Action Steps

Responsible Party

Timeline

Progress

6.1

Identify square footage and classroom configurations needed to provide instruction at East Campus

Executive Vice President; Dean, Off-Campus Programs

August – September, 2010

Completed

6.2

Research alternative locations to house the East Campus; obtain proposals and price quotes

Vice President, Business Services; Dean, Off-Campus Programs; District Director of General Services

October – December 2010

Completed

6.3

Narrow proposals and present best options to Chancellor's Cabinet for review

Vice Chancellor, Business Services; President

March 2011

Completed 

6.4

Identify core list of general education courses to offer in rotation in a fast-track format

Executive Vice President; Dean, Off-Campus Programs; Deans, Math & Science, Social Science & Humanities, Communication & Learning Resources

January – March 2011

Completed, June 2011 

6.5

Present lease contract for Board approval

Vice Chancellor, Business Services; President

February 2011

Completed, March 2011 

6.6

Develop new curriculum to prepare students for entry-level occupations using multi-functional machine "trainers" 

Vice President, Business Services; Assistant Dean, Career & Technical Education; Consultant 

February-May 2011 

On hold until August 2011 

6.7

Build out newly leased space in accordance with desired classroom configurations 

Property owner under the supervision of the Vice President, Business Services and the Director of Facilities, Maintenance & Operations 

March-May 2011

Completed

6.8

Move out of existing facilities; move in to and set up new facility 

Dean, Off-Campus Programs; Director of Facilities, Maintenance & Operations; Technology Support Services Supervisor, East Campus faculty and staff 

June-July 2011 

Completed 

Supporting Evidence

  1. Santa Paula/Fillmore Design Team Report
  2. Architectural Plans, Santa Paula Site